Fisheries management and monitoring of environmental impact on fish resources in the Baltic sea
Report ID: 159

1. In 2008 the Supreme Audit Institutions of Denmark, Estonia, Finland, Germany, Latvia, Lithuania, Poland, Russia, and Sweden conducted an audit of environmental monitoring and fisheries management and control in the Baltic Sea. The Supreme Audit Institutions in Estonia, Finland, Lithuania, Russia, and Sweden did not participate in the audit of the environmental monitoring in the Baltic Sea. The Supreme Audit Institutions of Latvia, Poland and Germany did not participate in the audit of fisheries management and control in the Baltic Sea. The audit was performed as a performance and compliance audit and covered the period 2005-2007.

2. The audit was divided into two parts: The first part was about environmental monitoring in the Baltic Sea and the second part was about fisheries management and control in the Baltic Sea.

3. The overall objective of the first part was to assess whether the signatory states of the Helsinki Convention are complying with the standards of the Cooperative Monitoring in the Baltic Marine Environment (COMBINE) and how the Baltic Sea Action Plan (BSAP) will affect national monitoring.

4. The overall objective of the second part was to conduct a review of fisheries management and control in the Baltic Sea.

5. The first and the second part of the audit share the following overall objective: How have the monitoring and fisheries control authorities contributed to preserve the marine environment and protect the fish stock in the Baltic Sea.

6. The relevant national legislation in the EU Member States is supposed to be within the frame set by the EU. However, the monitoring and fisheries management and control strategies may differ significantly among the individual countries, and comparative analyses may provide an overview of what is considered good practice. Furthermore, Russian fisheries legislation is, naturally, not adjusted to the EU-regulations. The Russian Federation’s national fishery legislation takes into consideration the requirements and provisions of nine international conventions and agreements related to fishery issues in the Baltic Sea. Moreover, Russia still adheres to the recommendations of the International Baltic Sea Fisheries Commission (IBSFC) in spite of the fact that it was dissolved in 2004.

7. The audit was planned and conducted as a parallel audit. A parallel audit means that the participating audit institutions audit the same audit objectives in their respective countries and identify relevant audit criteria and audit methods together. However, it is up to the individual supreme audit institution to decide how to conduct the audit and which audit criteria and audit methods to apply in the audit. The Joint Final Report is prepared on the basis of the data provided by the participating supreme audit institutions.

Joint Report of the International Coordinated audit of Chernobyl Shelter Fund
Report ID: 219

On April 26, 1986, the worst accident in the history of civilian nuclear power occurred at the Chernobyl Nuclear Power Plant in Ukraine, where an explosion destroyed the core of reactor Unit 4 containing approximately 200 tons of nuclear fuel. The explosion and heat from the reactor core propelled radioactive material as much as six miles high, where it was then dispersed mainly over 60,000 square miles of Ukraine, Belarus, and Russia. Smaller amounts of radioactive material spread over Eastern and Western Europe and Scandinavia and were even detected in the United States.

The Chernobyl Shelter Fund (CSF) was founded at European Bank for Reconstruction and Development (EBRD) in 1997 aimed at financing Shelter Implementation Plant (SIP).The Fund is guided by the set of rules regarding its resource management. Contributor Governments, mainly of G-7 and European Union, contribute to the Fund. The Assembly of Contributors supervises SIP implementation progress.

The Initial SIP costs were estimated at about USD 758 million (about EUR 585 million 4) in 1997. In 2003 and 2004 technical uncertainties and delays in the SIP fulfilment became apparent, especially with the construction of NSC, which resulted in cost escalation to EUR 840 million. The causes of those cost increases and the resulting need for additional steps to control cost and time overruns were discussed at all level including the Assemblies of Contributors. All G-85 Governments agreed to increase the scale of CSF.

Such increase was tied to the requirements to be fulfilled by Ukraine, including improvement of management, removal of procedural obstacles and timely delivery of Ukraine’s contributions. Thus, as of January 2006 estimated total costs were EUR 955 million and term for SIP completion was extended from 2005 to 2010.

Due to failure in timely realization of SIP, in 2006, the Special Subgroup on the Audit of Natural, Man-caused Disasters Consequences and Radioactive Wastes Elimination of the EUROSAI Working Group on Environmental Auditing decided to conduct an international coordinated audit of the Chernobyl Shelter Fund.

The aim of the audit was the establishment of actual state of affairs regarding legal, organizational and financial support of decommissioning the Chernobyl Nuclear Power Plant (CNPP) and transforming destroyed CNPP Unit 4 into an environmentally safe system by fulfilling the Shelter Implementation Plan.

Source: http://old.ac-rada.gov.ua/img/files/auditeurosai1.pdf