Parallel Audit on railway construction Zalalovo Bajansenye - Hodo Murska Sobota
Report ID: 189

The Hungarian-Slovenian railway link - between the Hungarian Zalalövő and the Slovenian Muraszombat (Murska Sobota) - was built between 1999 and 2001 as part of the V. European transit corridor.

Since the two countries adopted an agreement on co-operation when planning and realising the investment, in 2001 the Supreme Audit institutions of Slovenia and Hungary decided to carry out a parallel audit of the investment.

Both supreme audit institutions reviewed apart from regularity of planning the investment public procurement process and financing the investment, also the ecological aspect of railway construction and other impacts of the investment.

The joint report presents the activities referred to railway construction undertaken by both countries and it will show some comparable audit results (data on railway construction costs and the answer to the question: which country was more cost efficient), and present an assessment of effectiveness of the investment referred to achievement of planned objectives.

Source: https://docplayer.hu/10411470-Audit-report-on-railway-construction-zalalovo-bajansenye-hodos-murska-sobota.html

Public Procurement in Western Balkans Synthesis Report on the Parallel Performance Audit
Report ID: 392

The Joint Working Group on Audit Activities (JWGAA) was established in 2002 with a mandate to contribute to maintaining the working links and cooperation between the SAIs in the Contact Committee and the Presidents’ Network (candidate and potential candidate countries). The main goal of the group’s activities is to facilitate cooperation between the current and future member SAIs, to provide support and to help exchange experience in the process of institutional development, transition and negotiation on EU accession Chapter 32 (the ability to assume the obligations of membership in the area of financial control).

The Parallel Performance Audit (PPA) project under the umbrella of the JWGAA was initiated in 2014 (as PPA 1), when the member SAIs received training and coaching on performance audit practice. Based on experiences from this pilot project, a PPA 2 project was launched in 2016, to conduct a PPA of Public Procurement, an area generally susceptible to fraud and corruption, and as such, it is often the focus of attention from the general public.

From April 2016 to September 2017, the SAIs of Albania, Bosnia & Herzegovina, the former Yugoslav Republic of Macedonia, Kosovo*, Montenegro and Serbia, supported by the ECA and the Swedish National Audit Office (SNAO), which co-chairs the JWGAA, conducted a parallel audit aimed to identify system problems related to public procurement, and suggesting possible ways in which these problems can be tackled by their respective governments.

The audit environment of the six SAIs is characterized by a common historical heritage and a similar bureaucratic culture, a transition process, and ongoing reforms on the way to EU integration. The report presents a synthesis of general findings and conclusions from the parallel audit as well as how this cooperation process was developed.

Source: http://www.dri.co.me/1/doc/Synthesis%20Report%20on%20the%20parallel%20performance%20audit%20of%20public%20procurament%20in%20Western%20Balkans.pdf