Joint Report of the International Coordinated audit of Chernobyl Shelter Fund
Report ID: 219

On April 26, 1986, the worst accident in the history of civilian nuclear power occurred at the Chernobyl Nuclear Power Plant in Ukraine, where an explosion destroyed the core of reactor Unit 4 containing approximately 200 tons of nuclear fuel. The explosion and heat from the reactor core propelled radioactive material as much as six miles high, where it was then dispersed mainly over 60,000 square miles of Ukraine, Belarus, and Russia. Smaller amounts of radioactive material spread over Eastern and Western Europe and Scandinavia and were even detected in the United States.

The Chernobyl Shelter Fund (CSF) was founded at European Bank for Reconstruction and Development (EBRD) in 1997 aimed at financing Shelter Implementation Plant (SIP).The Fund is guided by the set of rules regarding its resource management. Contributor Governments, mainly of G-7 and European Union, contribute to the Fund. The Assembly of Contributors supervises SIP implementation progress.

The Initial SIP costs were estimated at about USD 758 million (about EUR 585 million 4) in 1997. In 2003 and 2004 technical uncertainties and delays in the SIP fulfilment became apparent, especially with the construction of NSC, which resulted in cost escalation to EUR 840 million. The causes of those cost increases and the resulting need for additional steps to control cost and time overruns were discussed at all level including the Assemblies of Contributors. All G-85 Governments agreed to increase the scale of CSF.

Such increase was tied to the requirements to be fulfilled by Ukraine, including improvement of management, removal of procedural obstacles and timely delivery of Ukraine’s contributions. Thus, as of January 2006 estimated total costs were EUR 955 million and term for SIP completion was extended from 2005 to 2010.

Due to failure in timely realization of SIP, in 2006, the Special Subgroup on the Audit of Natural, Man-caused Disasters Consequences and Radioactive Wastes Elimination of the EUROSAI Working Group on Environmental Auditing decided to conduct an international coordinated audit of the Chernobyl Shelter Fund.

The aim of the audit was the establishment of actual state of affairs regarding legal, organizational and financial support of decommissioning the Chernobyl Nuclear Power Plant (CNPP) and transforming destroyed CNPP Unit 4 into an environmentally safe system by fulfilling the Shelter Implementation Plan.

Source: http://old.ac-rada.gov.ua/img/files/auditeurosai1.pdf

International Coordinated Audit (Control) of Public Funds, Allocated to prevention and Consequences elimination of Disasters and Catastrophes
Report ID: 250

The International Coordinated Audit (Control) of Public Funds, Allocated to Prevention and consequences Elimination of Disasters and Catastrophes was included into the Work Plan of the EUROSAI Task Force on the Audit of Funds Allocated to Disasters and Catastrophes for 2012-2014, and was conducted by the SAIs of 9 participated countries.

The audit (control) objective was to assess legality and utilization efficiency of the public funds
allocated to establishment, functioning and development of the national system for prevention
and response to natural and man-caused disasters and catastrophes.

This audit also allowed to test Good Practice Recommendations for the Audit of Funds Allocated to Disasters and Catastrophes, which were developed by the Accounting Chamber of Ukraine within the framework of the EUROSAI Task Force and were prepared for approval in 2014.

EUROSAI WGEA COOPERATIVE AUDIT ON AIR QUALITY
Report ID: 251

With the aim to assess whether the governments of 16 european countries were taking proper action on air quality, the SAIs of the European Court of Auditors, Albania, Bulgaria, Estonia, Georgia, Hungary, Israel, Kosovo, Moldova, Poland, Romania, Slovakia, Spain, Switzerland, the Former Yugoslav Republic of Macedonia and the Netherlands conducted a cooperative audit.

In order to collect and assess comparable information on national government actions, the 15 SAIs
prepared a common audit framework containing the main audit question, the audit topics and the corresponding secondary questions to be addressed by the national audits. The main audit question was: “What is known about the effectiveness and efficiency of measures taken by national and local governments to improve air quality, and are these measures compliant with international and national legislation?”

Two of the main audit findings were that many European countries are failing to comply with international and European standards on air quality. Moreover, many governments have failed to take effective  action to improve air quality and hence to protect their citizens’ health.

 

 

AFROSAI-e _Collaborative Audit for Integrating Environmental Risks in an Audit at Local Government
Report ID: 263

During the 2015,  AFROSAI-E Governing Board and Technical Update Meetings, the role of SAIs in addressing critical environmental challenges through their day-day audit activities was discussed. They decided to design a simplistic way to use SAIs’ existing financial and human resources to identify possible areas of improvement supported by solution-driven  planning towards environmental focus and decide to conduct an Environmental Risk Project.

The SAIs of South Africa, Nigeria, Ghana, Botswana, Sierra Leone, Rwanda and Tanzania decided to participate in the program, which comprised, among others, the development of an e-learning programme, in collaboration with the Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ), the execution of parallel audits and the development of a joint publication.

Find attached (in a merged file) the joint publication explaining the project methodology, as well as the  AUDIT REPORT ON MANAGEMENT OF SOLID WASTE IN HUYE DISTRICT – 2016 preparared by SAI Ruanda, as a result of the audit conducted in the framework of the Project.

Source: https://afrosai-e.org.za/wp-content/uploads/2019/04/Integrating-Environmental-Audit-Risks-in-Audit-at-LG-level-Brochure1_00.pdf

Audit of Disaster Risk Reduction
Report ID: 267

WIthin the framework of the activities of the former INTOSAI Working Group on Accountability for and the Audit of Disaster–related Aid (AADA), from 2011 to 2013 the SAIs of Azerbaijan, Chile, India, Indonesia, Netherlands, Pakistan, Philippines, Romania, Turkey (coordinator) and Ukraine carried out a coordinated audit.

The aim of the audit was  to provide inputs for the draft versions of ISSAI 5510 "Audit of Disaster Risk Reduction" and testing and improving its content.

The joint report presents the results of the international parallel/coordinated audit in two sections:

• In part I: Joint report and common conclusions of the international parallel/coordinated audit.

• In part II: Summaries of the national audits were given.

Source: http://www.sayistay.gov.tr/en/?p=2&ContentID=234