Parallel audit of the use of public funds for motorway construction
Report ID: 65

The European motorway network forms the backbone of the passenger and freight transport in the European Union. As this situation will remain unchanged for the time being, investments in the expansion and maintenance of the European Motorway network are very important. Thus, examining the use of public funds for financing motorway construction projects is a key responsibility of Supreme Audit Institutions.

This report informs about the findings produced by the parallel audit missions regarding the funds spent on building the A 73 motorway (A 73) in Germany (section Thuringia/Bavaria satate border - Lichten - fels) and the D 1 motorway (D 1) in the Slovak Republic (section Vrtizer - Hricovske Podhradie). The audit missions focused on the public procurement procedure and a comparison of building standards and costs relative to the A 73 and the D 1. In the years 2009 to 2011, the audits were performed by the German SAI and the Slovak SAI in their respective country in order to share their findings and make comparisons.

The parallel audits found that by awarding the public works contract concerning the D 1 to a general contractor, competition was restricted placing small and medium sized enterprises at a disadvantage.

The expenses on building the two motorways increased considerably owing to the general increase in construction costs, the hike in value added tax (VAT) and, above all, the inadequate preparatory works performed by the respective national road works administrations. The two administrations did not or not adequately invite tenders for required work and services, with the result that supplementary agreements had to be subsequently concluded. Since the costs stipulated in these agreements were fixed in an environment with reduced or even no competition the contractors were able to enforce higher prices.

Special Report Management of a Cross-Border Broadband Initiative: the Bytel Project
Report ID: 280

This report is the result of a co-ordinated examination between the Office of the Comptroller and Auditor General and the Northern Ireland Audit Office to the Bytel project. The project was aimed to provide high-speed broadband connectivity linking Belfast, Craigavon, Armagh, Dundalk and Dublin It was supported by the European Union (EU) Interreg III programme, which ran from 2000 to 2006.

Due to the nature of the issues to be examined and that Bytel was located in Northern Ireland, the detailed work in relation to the grant payments was carried out by the NIAO. The NIAO's report is also attached as an appendix of the report. The report examines the role of the Department of Communications, Energy and Natural Resources in the management of the project.

Source: https://www.audit.gov.ie/en/Find-Report/Publications/Special%20Reports/Special-Report-90-Management-of-Cross-Border-Initiative-the-Bytel-Project.html

Parallel audit of the preparation of Poland and Ukraine for the organization of the European Football Championship "EURO 2012" tournament
Report ID: 305

The parallel audit on the preparation of Poland and Ukraine for the organization of the Final Tournament of the European Football Championship "UEFA 2012" was carried out at the initiative of the SAI of Poland and the SAI of Ukraine. The audit was carried out in the period 2009 to 2010 and had the scope of those years.

The purpose of the audit was to evaluate the state of implementation, coordination, supervision and financing of the tasks related to the preparation of Poland and Ukraine for the organization of the UEFA 2012, carried out by the corresponding authorities.

Source: https://rp.gov.ua/upload-files/IntCooperation/IntAudits/31-12-2010%2009-00-00/Zvit_UEFA_EURO_2012_2010.pdf

Report available in Polish and Ukranian